Project profile
Central Park Plaza Project · City Walk · prices, sales and rents
Registered prices, construction progress and the record across its buildings.
Developer: Citywalk Residential 1
Data to 4 November 2026
- Registered sales
- 4
- Last 12 months
- Median off-plan price
- —
- Per sq ft
- Construction progress
- 43.7%
- DLD end date Oct 2026
Dubai Land Department lists the project as under construction, 43.7% complete, with a DLD end date of 8 October 2026. In the last 12 months, Dubai Land Department registered 4 sales in Central Park Plaza, worth AED 10.2M in total.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence: registered sales and new rent contracts. Medians use at least 5 transactions.
A project, in progress.
Under construction
- Start
- 8 December 2023
- DLD end date
- 8 October 2026
- Units
- 212
- Buildings
- 2
DLD progress 43.7% (register read on 1 November 2026); the registered period (8 December 2023 to 8 October 2026) has ended, and the time since its start is 103% of it.
Launch and latest registrations.
- Launch price
- AED 3,203
- First 90 days from Jan 2024, 203 home sales
- Last 12 months
- —
- 4 home sales
- Change
- —
- Same home types, AED/sqft
Launch price is the median AED/sqft of off-plan home sales in the first 90 days after the first of them was registered, against the median of the project’s home sales in the last 12 months, ready and off-plan, leaving out any from those 90 days; plots and whole buildings count on neither side. The change compares the two periods home type by home type (class and bedrooms, at least 5 sales of a type on both sides), weighted by the later sales, so a shift from studios to larger homes does not read as a change in price; it is shown where those types hold at least 60% of the later sales. The two medians count every home sale, so their mix can differ.
Central Park Plaza registered prices, over time.
Median registered price, AED per sq ft
Show the figures
| Month |
|---|
| Aug 2024 |
| Sep 2024 |
| Oct 2024 |
| Nov 2024 |
| Dec 2024 |
| Jan 2025 |
| Feb 2025 |
| Mar 2025 |
| Apr 2025 |
| May 2025 |
| Jun 2025 |
| Jul 2025 |
| Aug 2025 |
| Sep 2025 |
| Oct 2025 |
| Nov 2025 |
| Dec 2025 |
| Jan 2026 |
| Feb 2026 |
| Mar 2026 |
| Apr 2026 |
| May 2026 |
| Jun 2026 |
| Jul 2026 |
Service charges.
In the area report.
The City Walk area report ranks the area’s projects by sales, each with its own owners’ association budget per sq ft a year where it publishes one, beside the area median by budget year.
See the City Walk area reportExplore the towers.
The latest registered sales in Central Park Plaza.
| Date | Unit | Size | Price | AED/sqft |
|---|---|---|---|---|
| 27 Jul 2026 | Apartment · Off-planTower B | 877 sqft | AED 2,781,000 | 3,171 |
| 13 Jul 2026 | Apartment · Off-planTower B | 860 sqft | AED 2,835,440 | 3,297 |
| 26 Jun 2026 | Apartment · Off-planTower A | 587 sqft | AED 1,849,705 | 3,151 |
| 19 Nov 2025 | Apartment · 1 bed · Off-planTower B | 877 sqft | AED 2,727,000 | 3,109 |
| 1 Oct 2025 | Apartment · 1 bed · Off-planTower A | 877 sqft | AED 2,727,100 | 3,110 |
| 26 Aug 2025 | Apartment · Off-planTower A | 4,470 sqft | AED 7,450,000 | 1,667 |
| 5 Aug 2025 | Apartment · Off-planTower B | 2,257 sqft | AED 8,875,000 | 3,932 |
| 3 Jun 2025 | Apartment · 5 beds · Off-planTower B | 7,212 sqft | AED 31,750,000 | 4,402 |
| 28 Mar 2025 | Apartment · Off-planTower B | 877 sqft | AED 3,300,000 | 3,763 |
| 11 Feb 2025 | Apartment · 5 beds · Off-planTower A | 9,444 sqft | AED 37,926,000 | 4,016 |
27 Jul 2026
ApartmentOff-plan877 sqft
Tower BAED 2,781,0003,171 AED/sqft
13 Jul 2026
ApartmentOff-plan860 sqft
Tower BAED 2,835,4403,297 AED/sqft
26 Jun 2026
ApartmentOff-plan587 sqft
Tower AAED 1,849,7053,151 AED/sqft
19 Nov 2025
Apartment1 bedOff-plan877 sqft
Tower BAED 2,727,0003,109 AED/sqft
1 Oct 2025
Apartment1 bedOff-plan877 sqft
Tower AAED 2,727,1003,110 AED/sqft
26 Aug 2025
ApartmentOff-plan4,470 sqft
Tower AAED 7,450,0001,667 AED/sqft
5 Aug 2025
ApartmentOff-plan2,257 sqft
Tower BAED 8,875,0003,932 AED/sqft
3 Jun 2025
Apartment5 bedsOff-plan7,212 sqft
Tower BAED 31,750,0004,402 AED/sqft
28 Mar 2025
ApartmentOff-plan877 sqft
Tower BAED 3,300,0003,763 AED/sqft
11 Feb 2025
Apartment5 bedsOff-plan9,444 sqft
Tower AAED 37,926,0004,016 AED/sqft
Questions about Central Park Plaza
How many homes were sold in Central Park Plaza in the last 12 months?
In the last 12 months, Dubai Land Department registered 4 sales in Central Park Plaza, worth AED 10.2M in total. Registered sales to 4 November 2026.
When is Central Park Plaza due to be completed?
Dubai Land Department lists the project as under construction, 43.7% complete, with a DLD end date of 8 October 2026. An end date is the date in the DLD register, not a handover forecast.
Where do these figures come from?
From Dubai Land Department open data, published on Dubai Data, to 4 November 2026: registered sales, new rent contracts and the project register. They are registered sales, not a valuation, and not investment advice.
To buy or rent
Looking to buy or rent in Central Park Plaza?
Leave your details and partner agents who work in Central Park Plaza can send you homes for sale or rent that match what you are looking for.