Skip to content

Project profile

Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5 Project · District One · prices, sales and rents

Registered prices, construction progress and the record across its buildings.

Developer: District One - FZ

Data to 4 November 2026

Registered sales
6
Last 12 months
Median ready price
AED 2,045
Per sq ft
Construction progress
100%
Completed

Dubai Land Department lists the project as completed on 6 October 2022. In the last 12 months, Dubai Land Department registered 6 sales in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5, worth AED 12.6M in total. The median price of ready homes was 2,045 AED/sqft.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence: registered sales and new rent contracts. Medians use at least 5 transactions.

Abstract illustration, not an architectural rendering

A project, in progress.

Construction progress100%

Completed

Start
1 December 2017
DLD end date
6 October 2022
Completion
6 October 2022
Units
73
Buildings
1

Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5 registered prices, over time.

Median registered price, AED per sq ft

Too few registered sales for a monthly price trend.

What does each home type sell and rent for in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5?

  • Apartment · 1 bed

    Ready median price
    —
    Median yearly rent
    AED 89K
    Gross yield
    Rent only

Last 12 months. Medians of at least 5 registered sales or new rent contracts; the median price of all sales mixes ready and off-plan. Gross yield is the median new yearly rent over the ready median price, shown where a home type has at least 10 ready sales and 5 new rents (“rent only” otherwise), before service charges and other costs.

Service charges.

In the area report.

The District One area report ranks the area’s projects by sales, each with its own owners’ association budget per sq ft a year where it publishes one, beside the area median by budget year.

See the District One area report

The latest registered sales in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5.

  • 28 Sep 2026

    Apartment1 bedReady752 sqft

    AED 1,450,0001,928 AED/sqft

  • 10 Jul 2026

    Apartment2 bedsReady1,308 sqft

    AED 2,500,0001,911 AED/sqft

  • 26 Feb 2026

    Apartment1 bedReady752 sqft

    AED 1,800,0002,394 AED/sqft

  • 25 Feb 2026

    Apartment2 bedsReady1,310 sqft

    AED 3,550,0002,710 AED/sqft

  • 9 Feb 2026

    Apartment1 bedReady767 sqft

    AED 1,740,0002,269 AED/sqft

  • 6 Feb 2026

    Apartment1 bedReady758 sqft

    AED 1,550,0002,045 AED/sqft

  • 3 Nov 2025

    Apartment1 bedReady756 sqft

    AED 1,660,0002,196 AED/sqft

  • 16 Oct 2025

    Apartment1 bedReady750 sqft

    AED 1,800,0002,400 AED/sqft

  • 29 Apr 2025

    Apartment3 bedsReady1,784 sqft

    AED 4,000,0002,242 AED/sqft

  • 12 Mar 2025

    Apartment1 bedReady758 sqft

    AED 1,700,0002,243 AED/sqft

Questions about Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5

What is the price per sq ft in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5?

In the 12 months to 4 November 2026, the median registered sale price of ready homes was 2,045 AED/sqft.

How many homes were sold in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5 in the last 12 months?

In the last 12 months, Dubai Land Department registered 6 sales in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5, worth AED 12.6M in total. The median price of ready homes was 2,045 AED/sqft. Registered sales to 4 November 2026.

What is the rent in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5?

In the 12 months to 4 November 2026, Apartment · 1 bed was the most rented home type in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5, at a median of AED 89,000 a year over 14 new contracts.

When was Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5 completed?

Dubai Land Department lists the project as completed on 6 October 2022.

Where do these figures come from?

From Dubai Land Department open data, published on Dubai Data, to 4 November 2026: registered sales, new rent contracts and the project register. They are registered sales, not a valuation, and not investment advice.

Looking to buy or rent in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5?

Leave your details and partner agents who work in Mohammed Bin Rashid Al Maktoum City, District One Phase III, Residences 5 can send you homes for sale or rent that match what you are looking for.

Privacy notice