Registered prices, construction progress and the record across its buildings.

Developer: Riviera Properties Development

Data to 4 November 2026

Registered sales
0
Last 12 months
Median off-plan price
—
Per sq ft
Construction progress
34.1%
DLD end date Feb 2027

Dubai Land Department lists the project as under construction, 34.1% complete, with a DLD end date of 12 February 2027. Dubai Land Department registered no sales in Nineteen Riviera Lagoon in the last 12 months.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence: registered sales and new rent contracts. Medians use at least 5 transactions.

Abstract illustration, not an architectural rendering

A project, in progress.

Construction progress34.1%

Under construction

Start
12 August 2024
DLD end date
12 February 2027
Units
19
Buildings
0

DLD progress 34.1% (register read on 1 November 2026); 89% of the registered period (12 August 2024 to 12 February 2027) has passed. How this is worked out

Launch and latest registrations.

Launch price
AED 2,328
First 90 days from Nov 2024, 5 home sales
Last 12 months
—
0 home sales
Change
—
Same home types, AED/sqft

Launch price is the median AED/sqft of off-plan home sales in the first 90 days after the first of them was registered, against the median of the project’s home sales in the last 12 months, ready and off-plan, leaving out any from those 90 days; plots and whole buildings count on neither side. The change compares the two periods home type by home type (class and bedrooms, at least 5 sales of a type on both sides), weighted by the later sales, so a shift from studios to larger homes does not read as a change in price; it is shown where those types hold at least 60% of the later sales. The two medians count every home sale, so their mix can differ.

Nineteen Riviera Lagoon registered prices, over time.

Median registered price, AED per sq ft

Too few registered sales for a monthly price trend.

Service charges.

In the area report.

The District 11 area report ranks the area’s projects by sales, each with its own owners’ association budget per sq ft a year where it publishes one, beside the area median by budget year.

See the District 11 area report

The latest registered sales in Nineteen Riviera Lagoon.

  • 27 Aug 2025

    Villa6 bedsOff-plan10,738 sqft

    AED 30,380,0002,829 AED/sqft

  • 25 Jul 2025

    Villa5 bedsOff-plan9,620 sqft

    AED 23,030,0002,394 AED/sqft

  • 26 May 2025

    Villa6 bedsOff-plan10,963 sqft

    AED 30,380,0002,771 AED/sqft

  • 26 May 2025

    Villa5 bedsOff-plan9,357 sqft

    AED 21,855,0002,336 AED/sqft

  • 18 Dec 2024

    Villa7 bedsOff-plan12,986 sqft

    AED 31,680,0002,440 AED/sqft

  • 18 Dec 2024

    Villa6 bedsOff-plan10,810 sqft

    AED 29,280,0002,709 AED/sqft

  • 18 Nov 2024

    Villa5 bedsOff-plan9,603 sqft

    AED 21,888,0002,279 AED/sqft

  • 14 Nov 2024

    Villa5 bedsOff-plan9,112 sqft

    AED 21,208,7502,328 AED/sqft

  • 14 Nov 2024

    Villa5 bedsOff-plan9,007 sqft

    AED 19,646,0002,181 AED/sqft

Questions about Nineteen Riviera Lagoon

When is Nineteen Riviera Lagoon due to be completed?

Dubai Land Department lists the project as under construction, 34.1% complete, with a DLD end date of 12 February 2027. An end date is the date in the DLD register, not a handover forecast.

Where do these figures come from?

From Dubai Land Department open data, published on Dubai Data, to 4 November 2026: registered sales, new rent contracts and the project register. They are registered sales, not a valuation, and not investment advice.