Data to 4 November 2026
- Registered sales
- 3
- Last 12 months
- Median off-plan price
- —
- Per sq ft
- Construction progress
- 36.2%
- DLD end date Jan 2026
Dubai Land Department lists the project as under construction, 36.2% complete, with a DLD end date of 31 January 2026. In the last 12 months, Dubai Land Department registered 3 sales in Trussardi Residences, worth AED 7.6M in total.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence: registered sales and new rent contracts. Medians use at least 5 transactions.
A project, in progress.
Under construction
- Start
- 1 February 2024
- DLD end date
- 31 January 2026
- Units
- 142
- Buildings
- 1
DLD progress 36.2% (register read on 1 November 2026); the registered period (1 February 2024 to 31 January 2026) has ended, and the time since its start is 138% of it.
Trussardi Residences registered prices, over time.
Median registered price, AED per sq ft
Show the figures
| Month | Off-plan (registered sales) |
|---|---|
| Oct 2024 | 1,600 AED/sqft 14 sales |
| Nov 2024 | 1,562 AED/sqft 5 sales |
| Dec 2024 | 1,611 AED/sqft 54 sales |
| Jan 2025 | — |
| Feb 2025 | — |
| Mar 2025 | — |
| Apr 2025 | 1,161 AED/sqft 28 sales |
| May 2025 | — 3 sales |
| Jun 2025 | — |
| Jul 2025 | — 2 sales |
| Aug 2025 | — 1 sale |
| Sep 2025 | — 4 sales |
| Oct 2025 | — |
| Nov 2025 | — |
| Dec 2025 | — 1 sale |
| Jan 2026 | — |
| Feb 2026 | — |
| Mar 2026 | — |
| Apr 2026 | — 1 sale |
| May 2026 | — |
| Jun 2026 | — |
| Jul 2026 | — |
| Aug 2026 | — |
| Sep 2026 | — 1 sale |
Service charges.
In the area report.
The Al Furjan area report ranks the area’s projects by sales, each with its own owners’ association budget per sq ft a year where it publishes one, beside the area median by budget year.
See the Al Furjan area reportThe latest registered sales in Trussardi Residences.
| Date | Unit | Size | Price | AED/sqft |
|---|---|---|---|---|
| 10 Sep 2026 | Apartment · 2 beds · Off-plan | 2,083 sqft | AED 2,981,420 | 1,431 |
| 7 Apr 2026 | Apartment · 2 beds · Off-plan | 1,817 sqft | AED 3,159,359 | 1,739 |
| 11 Dec 2025 | Apartment · 1 bed · Off-plan | 872 sqft | AED 1,454,670 | 1,668 |
| 23 Sep 2025 | Apartment · 1 bed · Off-plan | 872 sqft | AED 1,400,000 | 1,606 |
| 23 Sep 2025 | Apartment · 1 bed · Off-plan | 818 sqft | AED 953,879 | 1,166 |
| 22 Sep 2025 | Apartment · 2 beds · Off-plan | 1,266 sqft | AED 1,491,607 | 1,178 |
| 1 Sep 2025 | Apartment · 2 beds · Off-plan | 1,960 sqft | AED 3,323,099 | 1,695 |
| 25 Aug 2025 | Apartment · 2 beds · Off-plan | 1,960 sqft | AED 3,229,988 | 1,648 |
| 22 Jul 2025 | Apartment · 1 bed · Off-plan | 916 sqft | AED 1,950,000 | 2,129 |
| 11 Jul 2025 | Apartment · 2 beds · Off-plan | 2,087 sqft | AED 3,442,227 | 1,649 |
10 Sep 2026
Apartment2 bedsOff-plan2,083 sqft
AED 2,981,4201,431 AED/sqft
7 Apr 2026
Apartment2 bedsOff-plan1,817 sqft
AED 3,159,3591,739 AED/sqft
11 Dec 2025
Apartment1 bedOff-plan872 sqft
AED 1,454,6701,668 AED/sqft
23 Sep 2025
Apartment1 bedOff-plan872 sqft
AED 1,400,0001,606 AED/sqft
23 Sep 2025
Apartment1 bedOff-plan818 sqft
AED 953,8791,166 AED/sqft
22 Sep 2025
Apartment2 bedsOff-plan1,266 sqft
AED 1,491,6071,178 AED/sqft
1 Sep 2025
Apartment2 bedsOff-plan1,960 sqft
AED 3,323,0991,695 AED/sqft
25 Aug 2025
Apartment2 bedsOff-plan1,960 sqft
AED 3,229,9881,648 AED/sqft
22 Jul 2025
Apartment1 bedOff-plan916 sqft
AED 1,950,0002,129 AED/sqft
11 Jul 2025
Apartment2 bedsOff-plan2,087 sqft
AED 3,442,2271,649 AED/sqft
Questions about Trussardi Residences
How many homes were sold in Trussardi Residences in the last 12 months?
In the last 12 months, Dubai Land Department registered 3 sales in Trussardi Residences, worth AED 7.6M in total. Registered sales to 4 November 2026.
When is Trussardi Residences due to be completed?
Dubai Land Department lists the project as under construction, 36.2% complete, with a DLD end date of 31 January 2026. An end date is the date in the DLD register, not a handover forecast.
Where do these figures come from?
From Dubai Land Department open data, published on Dubai Data, to 4 November 2026: registered sales, new rent contracts and the project register. They are registered sales, not a valuation, and not investment advice.