- Registered sales
- 8
- Last 12 months
- Median ready price
- — Too few registered as homes
- Per sq ft
- Construction progress
- 68.5%
- DLD end date Dec 2027
Dubai Land Department lists the project as under construction, 68.5% complete, with a DLD end date of 31 December 2027. In the last 12 months, Dubai Land Department registered 8 sales in Sobha Estates, worth AED 203.2M in total. No ready median per sq ft: DLD registers most ready sales here as plots or whole buildings, and too few as homes.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence: registered sales and new rent contracts. Medians use at least 5 transactions.
A project, in progress.
Under construction
- Start
- 10 October 2023
- DLD end date
- 31 December 2027
- Units
- 0
- Buildings
- 0
DLD progress 68.5% (register read on 1 November 2026); 73% of the registered period (10 October 2023 to 31 December 2027) has passed.
Sobha Estates registered prices, over time.
Median registered price, AED per sq ft
Too few registered sales for a monthly price trend.
Service charges.
In the area report.
The Bukadra area report ranks the area’s projects by sales, each with its own owners’ association budget per sq ft a year where it publishes one, beside the area median by budget year.
See the Bukadra area reportThe latest registered sales in Sobha Estates.
| Date | Unit | Size | Price | AED/sqft |
|---|---|---|---|---|
| 24 Aug 2026 | Plot · Ready | 8,288 sqft | AED 18,450,000 | 2,226 |
| 14 Jul 2026 | Plot · Ready | 8,469 sqft | AED 25,717,140 | 3,037 |
| 26 Mar 2026 | Plot · Ready | 8,503 sqft | AED 24,700,000 | 2,905 |
| 26 Jan 2026 | Plot · Ready | 8,351 sqft | AED 29,719,242 | 3,559 |
| 26 Nov 2025 | Plot · Ready | 8,308 sqft | AED 25,775,580 | 3,103 |
| 20 Nov 2025 | Plot · Ready | 8,481 sqft | AED 27,431,616 | 3,234 |
| 19 Nov 2025 | Plot · Ready | 8,288 sqft | AED 25,717,140 | 3,103 |
| 10 Nov 2025 | Plot · Ready | 8,288 sqft | AED 25,717,140 | 3,103 |
| 20 Oct 2025 | Plot · Ready | 8,288 sqft | AED 25,300,000 | 3,053 |
| 1 Oct 2025 | Plot · Ready | 8,288 sqft | AED 25,717,140 | 3,103 |
24 Aug 2026
PlotReady8,288 sqft
AED 18,450,0002,226 AED/sqft
14 Jul 2026
PlotReady8,469 sqft
AED 25,717,1403,037 AED/sqft
26 Mar 2026
PlotReady8,503 sqft
AED 24,700,0002,905 AED/sqft
26 Jan 2026
PlotReady8,351 sqft
AED 29,719,2423,559 AED/sqft
26 Nov 2025
PlotReady8,308 sqft
AED 25,775,5803,103 AED/sqft
20 Nov 2025
PlotReady8,481 sqft
AED 27,431,6163,234 AED/sqft
19 Nov 2025
PlotReady8,288 sqft
AED 25,717,1403,103 AED/sqft
10 Nov 2025
PlotReady8,288 sqft
AED 25,717,1403,103 AED/sqft
20 Oct 2025
PlotReady8,288 sqft
AED 25,300,0003,053 AED/sqft
1 Oct 2025
PlotReady8,288 sqft
AED 25,717,1403,103 AED/sqft
Questions about Sobha Estates
How many homes were sold in Sobha Estates in the last 12 months?
In the last 12 months, Dubai Land Department registered 8 sales in Sobha Estates, worth AED 203.2M in total. No ready median per sq ft: DLD registers most ready sales here as plots or whole buildings, and too few as homes. Registered sales to 4 November 2026.
When is Sobha Estates due to be completed?
Dubai Land Department lists the project as under construction, 68.5% complete, with a DLD end date of 31 December 2027. An end date is the date in the DLD register, not a handover forecast.
Where do these figures come from?
From Dubai Land Department open data, published on Dubai Data, to 4 November 2026: registered sales, new rent contracts and the project register. They are registered sales, not a valuation, and not investment advice.
To buy or rent
Looking to buy or rent in Sobha Estates?
Leave your details and partner agents who work in Sobha Estates can send you homes for sale or rent that match what you are looking for.