Alba Tower Project · Jumeirah Garden City · prices, sales and rents

Registered prices, construction progress and the record across its buildings.

Developer: Century Seven Properties

Data to 4 November 2026

Registered sales
15
Last 12 months
Median off-plan price
AED 1,773
Per sq ft
Construction progress
30.9%
DLD end date Jun 2028

Dubai Land Department lists the project as under construction, 30.9% complete, with a DLD end date of 30 June 2028. In the last 12 months, Dubai Land Department registered 15 sales in Alba Tower, worth AED 15.2M in total. The median off-plan price was 1,773 AED/sqft.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence: registered sales and new rent contracts. Medians use at least 5 transactions.

Abstract illustration, not an architectural rendering

A project, in progress.

Construction progress30.9%

Under construction

Start
30 September 2024
DLD end date
30 June 2028
Units
73
Buildings
1

DLD progress 30.9% (register read on 1 November 2026); 56% of the registered period (30 September 2024 to 30 June 2028) has passed. How this is worked out

Launch and latest registrations.

Launch price
AED 1,227
First 90 days from Feb 2025, 10 home sales
Last 12 months
AED 1,773
15 home sales
Change
+7.7%
Same home types, AED/sqft

Launch price is the median AED/sqft of off-plan home sales in the first 90 days after the first of them was registered, against the median of the project’s home sales in the last 12 months, ready and off-plan, leaving out any from those 90 days; plots and whole buildings count on neither side. The change compares the two periods home type by home type (class and bedrooms, at least 5 sales of a type on both sides), weighted by the later sales, so a shift from studios to larger homes does not read as a change in price; it is shown where those types hold at least 60% of the later sales. The two medians count every home sale, so their mix can differ.

Alba Tower registered prices, over time.

Median registered price, AED per sq ft

Too few registered sales for a monthly price trend.

What does each home type sell and rent for in Alba Tower?

  • Apartment · 1 bed

    Median price, all sales
    AED 721.8K
    AED/sqft
    1,452
    Sales
    9
  • Apartment · 2 beds

    Median price, all sales
    AED 1.3M
    AED/sqft
    1,791
    Sales
    6

Last 12 months. Prices are medians of at least 5 registered sales, ready and off-plan together.

Service charges.

In the area report.

The Jumeirah Garden City area report ranks the area’s projects by sales, each with its own owners’ association budget per sq ft a year where it publishes one, beside the area median by budget year.

See the Jumeirah Garden City area report

The latest registered sales in Alba Tower.

  • 30 Oct 2026

    Apartment2 bedsOff-plan748 sqft

    AED 1,326,2221,773 AED/sqft

  • 11 Sep 2026

    Apartment1 bedOff-plan416 sqft

    AED 810,0001,947 AED/sqft

  • 15 Jul 2026

    Apartment1 bedOff-plan446 sqft

    AED 904,9012,029 AED/sqft

  • 15 Jul 2026

    Apartment1 bedOff-plan567 sqft

    AED 889,5031,569 AED/sqft

  • 15 Jul 2026

    Apartment1 bedOff-plan448 sqft

    AED 844,0971,884 AED/sqft

  • 15 Jul 2026

    Apartment1 bedOff-plan508 sqft

    AED 721,8111,421 AED/sqft

  • 9 Apr 2026

    Apartment2 bedsOff-plan686 sqft

    AED 1,300,0001,895 AED/sqft

  • 9 Apr 2026

    Apartment1 bedOff-plan482 sqft

    AED 700,0001,452 AED/sqft

  • 9 Apr 2026

    Apartment1 bedOff-plan482 sqft

    AED 645,9391,340 AED/sqft

  • 9 Apr 2026

    Apartment1 bedOff-plan482 sqft

    AED 639,5391,327 AED/sqft

Questions about Alba Tower

What is the price per sq ft in Alba Tower?

In the 12 months to 4 November 2026, the median registered off-plan sale price was 1,773 AED/sqft.

How many homes were sold in Alba Tower in the last 12 months?

In the last 12 months, Dubai Land Department registered 15 sales in Alba Tower, worth AED 15.2M in total. The median off-plan price was 1,773 AED/sqft. Registered sales to 4 November 2026.

When is Alba Tower due to be completed?

Dubai Land Department lists the project as under construction, 30.9% complete, with a DLD end date of 30 June 2028. An end date is the date in the DLD register, not a handover forecast.

Where do these figures come from?

From Dubai Land Department open data, published on Dubai Data, to 4 November 2026: registered sales, new rent contracts and the project register. They are registered sales, not a valuation, and not investment advice.