Skip to content

Project profile

Creek Bay Project · Dubai Creek Harbour · prices, sales and rents

Registered prices, construction progress and the record across its buildings.

Developer: Dubai Creek Harbour

Registered salesLast 12 months
703
Median off-plan pricePer sq ft
AED 2,740
Construction progressDLD end date Apr 2030
0.6%

Data to 4 November 2026

Dubai Land Department lists the project as under construction, 0.6% complete, with a DLD end date of 30 April 2030. In the last 12 months, Dubai Land Department registered 703 sales in Creek Bay, worth AED 2.3B in total. The median off-plan price was 2,740 AED/sqft.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence: registered sales and new rent contracts. Medians use at least 5 transactions.

Abstract illustration, not an architectural rendering

A project, in progress.

Construction progress0.6%

Under construction

Start
31 March 2026
DLD end date
30 April 2030
Units
766
Buildings
3

DLD progress 0.6% (register read on 1 November 2026); 15% of the registered period (31 March 2026 to 30 April 2030) has passed. How this is worked out

3 buildings in the DLD register, 2 with a page here.

Launch and latest registrations.

Launch priceFirst 90 days from Dec 2025, 200 home sales
AED 2,700
After the first 90 days503 home sales
AED 2,766
ChangeSame home types, AED/sqft
+1.8%

Launch price is the median AED/sqft of off-plan home sales in the first 90 days after the first of them was registered, against the median of the project’s home sales in the last 12 months, ready and off-plan, leaving out any from those 90 days; plots and whole buildings count on neither side. The change compares the two periods home type by home type (class and bedrooms, at least 5 sales of a type on both sides), weighted by the later sales, so a shift from studios to larger homes does not read as a change in price; it is shown where those types hold at least 60% of the later sales. The two medians count every home sale, so their mix can differ.

Creek Bay registered prices, over time.

Median registered price, AED per sq ft

Median price per sq ft of registered sales of apartments, by month. Months with fewer than 5 sales are left as gaps.
Show the figures
Month Off-plan (registered sales)
Dec 2025 — 2 sales
Jan 2026 2,703 AED/sqft 144 sales
Feb 2026 2,525 AED/sqft 48 sales
Mar 2026 3,153 AED/sqft 13 sales
Apr 2026 2,763 AED/sqft 313 sales
May 2026 2,606 AED/sqft 42 sales
Jun 2026 2,687 AED/sqft 31 sales
Jul 2026 3,073 AED/sqft 35 sales
Aug 2026 2,564 AED/sqft 48 sales
Sep 2026 2,371 AED/sqft 15 sales
Oct 2026 2,673 AED/sqft 12 sales

What does each home type sell and rent for in Creek Bay?

  • Apartment · 1 bed

    Median price, all sales
    AED 2M
    AED/sqft
    2,662
    Sales
    325
  • Apartment · 2 beds

    Median price, all sales
    AED 3.8M
    AED/sqft
    3,031
    Sales
    295
  • Apartment · 3 beds

    Median price, all sales
    AED 5.9M
    AED/sqft
    3,207
    Sales
    83

Last 12 months. Prices are medians of at least 5 registered sales, ready and off-plan together.

Service charges.

In the area report.

The Dubai Creek Harbour area report ranks the area’s projects by sales, each with its own owners’ association budget per sq ft a year where it publishes one, beside the area median by budget year.

See the Dubai Creek Harbour area report

Explore the towers.

The latest registered sales in Creek Bay.

  • 28 Oct 2026

    Apartment1 bedOff-plan761 sqft

    Tower B

    AED 2,033,8882,673 AED/sqft

  • 26 Oct 2026

    Apartment3 bedsOff-plan757 sqft

    Tower B

    AED 5,774,8887,629 AED/sqft

  • 23 Oct 2026

    Apartment2 bedsOff-plan1,448 sqft

    Tower B

    AED 3,438,8882,375 AED/sqft

  • 20 Oct 2026

    Apartment2 bedsOff-plan1,432 sqft

    Tower B

    AED 4,484,8883,132 AED/sqft

  • 14 Oct 2026

    Apartment3 bedsOff-plan1,855 sqft

    Tower B

    AED 5,614,8883,027 AED/sqft

  • 14 Oct 2026

    Apartment3 bedsOff-plan1,855 sqft

    Tower B

    AED 5,603,8883,021 AED/sqft

  • 14 Oct 2026

    Apartment2 bedsOff-plan1,432 sqft

    Tower B

    AED 4,401,8883,074 AED/sqft

  • 13 Oct 2026

    Apartment2 bedsOff-plan1,448 sqft

    Tower B

    AED 3,415,8882,359 AED/sqft

  • 7 Oct 2026

    Apartment2 bedsOff-plan1,448 sqft

    Tower A

    AED 3,432,8882,371 AED/sqft

  • 2 Oct 2026

    Apartment2 bedsOff-plan1,432 sqft

    Tower B

    AED 4,272,6902,984 AED/sqft

Questions about Creek Bay

What is the price per sq ft in Creek Bay?

In the 12 months to 4 November 2026, the median registered off-plan sale price was 2,740 AED/sqft.

How many homes were sold in Creek Bay in the last 12 months?

In the last 12 months, Dubai Land Department registered 703 sales in Creek Bay, worth AED 2.3B in total. The median off-plan price was 2,740 AED/sqft. Registered sales to 4 November 2026.

When is Creek Bay due to be completed?

Dubai Land Department lists the project as under construction, 0.6% complete, with a DLD end date of 30 April 2030. An end date is the date in the DLD register, not a handover forecast.

Where do these figures come from?

From Dubai Land Department open data, published on Dubai Data, to 4 November 2026: registered sales, new rent contracts and the project register. They are registered sales, not a valuation, and not investment advice.

Developer's image · Emaar Properties

Looking to buy or rent in Creek Bay?

Leave your details and partner agents who work in Creek Bay can send you homes for sale or rent that match what you are looking for.

Privacy notice